Attached is a sneak-peak of our ongoing construction activities at 149 Greenkill Avenue and 124 Franklin Street…we have been busy!
As of March 2022, construction at 149 Greenkill just passed the 50% complete mark, on budget and schedule!
124 Franklin has been gutted in preparation for a full renovation, and our demolition of a structurally unsound rear addition has been completed. In addition, we repaired the utility lines, so the home has water for the first time in over 20 years!
Overall, our activities on this last phase of our PILOT program is progressing as planned and on schedule. We expect to make a major announcement on our Greenkill home soon.